Frustration grows over ‘deeply disappointing’ delays to Newton Abbot Market Hall


Despite construction finishing in the summer, Newton Abbot’s £5 million town centre market hall remains closed after the council raised concerns over its preferred operator
Fresh concerns have been raised over the future of Newton Abbot’s new £5 million town centre market hall after more delays were announced.
The building, redeveloped using money from the Government's Future High Streets Fund, was completed in the summer after nearly two years of work, but as yet it has not reopened for business despite calls from councillors for a Christmas opening.
With a festive relaunch ruled out, there had been hopes that Teignbridge District Council would sort out the management of the new market hall by early in the new year, but those hopes now appear to have been dashed too.
Even a spring opening could be in jeopardy.
The council says it has been working with a preferred bidder to run the venue, but after "extensive discussions, checks and assessments" it is not fully satisfied that the proposals would provide a secure long-term future.
It has formally informed the bidder that it is reviewing all available options and is awaiting advice from industry specialists, though talks with the prospective operator remain ongoing.
In a bid to speed up the opening, the council is now considering completing the remaining internal fit-out works itself before handing the building over.
Previously, it had planned to wait until an operator was appointed so they could help design the interior.
However, angry councillors are demanding answers over the delays, with two lodging urgent questions ahead of an overview and scrutiny meeting next week as frustrations grow.
Cllr David Palethorpe, Deputy Leader and Executive Member for Economy, Estates and Major Projects, said: "We know residents, traders and businesses are eager to see the market hall open, and we share their frustration that this has taken longer than expected.
"The redevelopment has delivered a significant improvement to this important historic building, but completing the construction work was only part of the challenge. We also need to make sure the market hall can operate successfully in the long term.
"Reviewing our options gives us the opportunity to consider the best way forward, including whether the council should undertake the remaining fit-out works."
Cllr Liam Mullone (Ind, College) warned a recent council meeting that Newton Abbot was in danger of becoming a market town with no market, while Cllr Janet Bradford said it had become "a deeply disappointing experience".
A meeting of the council’s Overview and Scrutiny Committee next week (November 24) will hear a call from Cllr Phil Bullivant (Con, Bradley) for an urgent public debate on the market hall project, as well as one from Cllr Jane Taylor (Ind, Kerswell-with-Coombe) calling for a review of the entire process.
Cllr Taylor pointed out: "The public have expressed not merely concern, but dismay, that an 800-year-old market town has no market and that continued delays mean it is increasingly unlikely to re-establish itself quickly.
"Many market traders have either retired or been forced into shops. It is an area of poor performance across a number of departments, from estates and economy to strategy and finance. Strategy in particular has been underwhelming."